UAE Information Assurance Regulation
T2.2.5
Working in Secure Areas
Priority
Applicability
P3
Based on risk assessment
Control
The entity shall design physical protection and guidelines for working in
secure areas.
Sub-Control
The entity shall:
1) establish guidelines for working in secure areas
2) make sure all personnel accessing secure areas is aware and accepts
rules and guidelines
3) supervise activities in secure areas
4) control access of devices to secure areas (See also T5.7.1)
Implementation Guidance (for information purpose only)
The following guidelines should be considered:
a. personnel should only be aware of the existence of, or activities within, a secure area on a need to
know basis;
b. unsupervised working in secure areas should be avoided both for safety reasons and to prevent
opportunities for malicious activities;
c. vacant secure areas should be physically locked and periodically checked;
d. photographic, video, audio or other recording equipment, such as cameras in mobile devices, should
not be allowed, unless authorized;
The arrangements for working in secure areas include controls for the employees, contractors and third
party users working in the secure area, as well as other third party activities taking place there
T2.2.6
Public Access, Delivery,
and Loading Areas
Priority
Applicability
P3
Based on risk assessment
Control
The entity shall control access points such as delivery and loading areas
and other points.
Sub-Control
The entity shall:
1) establish access procedures to loading and unloading areas to restrict
access to only authorized personnel
2) physically segregate loading and unloading activities
3) inspect and register incoming and outgoing material in accordance
with the entity’s asset management procedures
Implementation Guidance (for information purpose only)
The following guidelines should be considered:
a. access to a delivery and loading area from outside of the building should be restricted to identified
and authorized personnel;
b. the delivery and loading area should be designed so that supplies can be unloaded without delivery
personnel gaining access to other parts of the building;
c. the external doors of a delivery and loading area should be secured when the internal doors are
opened;
d. incoming material should be inspected for potential threats before this material is moved from the
delivery and loading area to the point of use;
e. incoming material should be registered in accordance with asset management procedures on entry to
the site;
f. incoming and outgoing shipments should be physically segregated, where possible