Part 3
Three Pillars of Japan’s Defense (Means to Achieve the Objectives of Defense)
wing aircraft stationed at MCAS Futenma will be located
near the elements with which they train, operate, or otherwise
work on a regular basis.
(4)Completion of Environmental Impact Assessment
Procedures
Chapter
2
Japan-U.S. Alliance
The MOD sent the environmental impact assessment scoping
document in 2007 to the Governor of Okinawa and other
parties. After the MOD worked on revising the document
based on the opinions provided by the governor, the MOD
completed the environmental impact assessment procedures
by sending the revised assessment document to related parties
including the governor in December 2012, while making the
assessment document available for public review. Throughout
these procedures, the MOD received a total of 1,561 opinions
from the Governor of Okinawa on six occasions, made all the
required revisions, and reflected them in the content of the
environmental assessment. In this way, the MOD had taken
steps to comply with relevant laws, asked opinions and ideas
from Okinawa Prefecture over a sufficient period of time, and
reflected them in the assessment.
(5)Promotion of the Futenma Replacement Facility
Construction Project
a. Suits over the Revocation of the Land-Fill Permit
The Director General of the Okinawa Defense Bureau
submitted the land-fill permit request on public waters to
Okinawa Prefecture in March 2013, and then Governor
of Okinawa Nakaima approved this in December 2013.
However, then Governor of Okinawa Onaga revoked the
land-fill permit by then Governor of Okinawa Nakaima in
October 2015, leading to the filing of three suits over the
revocation of the land-fill permit between the Government of
Japan and Okinawa Prefecture.7
Under these circumstances, the court came up with a
settlement recommendation, and the Government of Japan
and Okinawa Prefecture reached a court-mediated settlement
agreement in March 2016. In the settlement, the Government
of Japan and Okinawa mutually affirmed that after the final
judicial ruling is handed down by the Supreme Court, they
would abide by the ruling and take steps in line with the spirit
of the text of the ruling and the reasons conducive to the text,
and continue to take responses in good faith by cooperating
with each other in accordance with the purpose of the ruling.
Pursuant to the provisions of the settlement agreement,
the Director General of the Okinawa Defense Bureau
7
327
immediately suspended the land-fill work while the Minister
of Land, Infrastructure, Transport and Tourism issued an
instruction for correction based on the Local Autonomy
Act to then Governor Onaga to repeal the revocation of
the land-fill permit. Subsequently, in December 2016, after
examination by the Central and Local Government Dispute
Management Council and deliberation by the Naha Branch
of the Fukuoka High Court, the Supreme Court set forth the
decision that the revocation of the land-fill permit by then
Governor Onaga was illegal.
b. Judgment of the Supreme Court
In the judgment, the Supreme Court ruled that then Governor
Nakaima’s decision was not illegal. The court stated that no
circumstances could be found indicating that then Governor
Nakaima’s decision that the landfill was in compliance with
the condition in Article 4 (1) (i) of the Act on Reclamation
of Publicly-owned Water Surface, “that it is appropriate and
reasonable as the use of national land,” had no foundation
in fact, or clearly lacked reasoning under socially accepted
conventions. The reasons given by the court include: (1)
the area of the replacement facilities and the landfill area
will be significantly reduced from the area of the MCAS
Futenma facilities, and (2) aircraft flying over residential
areas can be avoided by the land-fill in the coastal area that
puts the runway extension out to the sea, and the replacement
facilities will be installed using part of Camp Schwab, which
is already provided to the U.S. Forces.
Moreover, regarding whether the construction of
replacement facilities takes environmental protection and
other considerations into adequate account, the Supreme
Court, finding that construction methods, environmental
protection measures and countermeasures that can conceivably
be taken at this point in time have been taken and that there is
sufficient consideration for disaster prevention, determined
that it cannot be said that then Governor Nakaima’s decision
was illegal. The court did not find that there was anything
particularly unreasonable in then Governor Nakaima’s
decision-making process and the content of the decision that
the construction met the condition of Article 4 (1) (ii) of the
Act on Reclamation of Publicly-owned Water Surface, “the
land-fill gives sufficient consideration to the protection of the
environment and prevention of disasters.”
c. Retraction of the Revocation of the Land-Fill Permit
Following this Supreme Court ruling, in December 2016,
then Governor Onaga retracted the revocation of the landfill permit and the Okinawa Defense Bureau resumed the
(1) The suit, filed by the Government of Japan as plaintiff based on Article 245-8 of the Local Autonomy Act, seeking a court ruling instructing a retraction of the revocation of the land-fill
permit by Governor Onaga (the so-called subrogation suit); (2) the suit, filed by Okinawa Prefecture based on Article 251-5 of the Local Autonomy Act, seeking to invalidate the decision to
suspend the validity of the revocation of the land-fill permit (the decision to stay execution) by the Minister of Land, Infrastructure, Transport and Tourism as the illegal “involvement of the
state”; and (3) the suit, filed by Okinawa Prefecture based on Article 3 of the Administrative Case Litigation Act, seeking to invalidate the decision to stay execution by the Minister of Land,
Infrastructure, Transport and Tourism.