Optimizing Equipment Procurement
Section
3
❶
Optimizing Equipment Procurement
Project Management throughout Equipment Life Cycle
1 Acquisition of Defense Equipment through Focused
Project Management
end of March 2020. The MOD designated Project Managers
(PMs) dedicated to specific major programs. At the same
time, the MOD established a systematic project management
system by setting up the Integrated Project Team (IPT),
which is composed of officials from relevant divisions within
the MOD.
So far (as of the end of March 2020), for 23 items that have
been selected for major and semi-major programs, the MOD
has formulated the Acquisition Strategy and the Acquisition
Plan (hereinafter referred to as “Acquisition Strategy, etc.”),
which specify the basic matters necessary to systematically
implement project management, such as the purpose of the
acquisition program, acquisition policy, and life cycle cost.
The Acquisition Strategy, etc. shows strategic plans to realize
optimized acquisitions of equipment.
Furthermore, in principle, ATLA annually confirms the
project implementation status with each SDF service, and
endeavors to promote appropriate project management
reflecting the latest situation by developing Analysis and
Evaluation, which compile changes made in acquisition plans
2
●
from the previous fiscal year, and thus reviews Acquisition
Strategy. In August 2019, Analysis and Evaluation of the
acquisition programs were implemented for 19 items for
which the Acquisition Strategy, etc. had been developed.
See
Fig. IV-2-3-1 (Equipment for Project Management and
Equipment for Semi-Project Management)
Chapter
2
2 Initiatives to Promote and Strengthen Project
Management
(1) Past Initiatives
The following initiatives have been implemented to promote
and strengthen project management.
a. Cost and Schedule Management Using WBS
For certain kinds of equipment produced in Japan, the MOD
promotes the introduction of a management method to visualize
the progress of work and cost generated by component (Work
Breakdown Structure [WBS])2 and endeavors to manage cost
and schedule to detect the signs of cost increase and schedule
delay early so that swift measures can be taken.
b. Method for More Accurate Cost Estimate
Life cycle cost and other costs have been estimated based on
actual cost data of similar equipment developed or introduced in
the past. However, as a larger amount of cost data is needed for
a more accurate estimate, the MOD promotes the establishment
of a cost database by collecting cost data and accumulating them
into a database.
c. Accumulation and Development of Expertise through Strengthened
Cooperation with Research and Educational Institutions, etc.
For further improving the management skills of PMs and
enhancing human resources among those who engage in project
management, the MOD strengthens collaboration with research
and educational institutions on project management and
provides opportunities to study project management methods
from overseas and the private sector on a regular basis.
A semi-major project is an acquisition project of specific equipment with a limited application of project management without the designation of PM and IPT, focusing on risks in functions,
performance, costs, schedules and other risk factors as in the case of equipment for project management.
WBS is a hierarchical structure used to practice project management that systematically divides the project into manageable units, in which the schedule and cost of each deliverable
(components and services) are allocated.
Defense of Japan
430
Measures on Defense Equipment and Technology
As defense equipment is becoming more sophisticated and
complex, its entire life cycle (concept study, research and
development, mass production, deployment, operation and
maintenance) cost has a tendency to increase in recent years.
It has become extremely important to streamline acquisition
throughout the life cycle of equipment and to establish
a systematic management to realize the streamlining in
order to efficiently acquire equipment of assured quality at
appropriate cost in a required timeline as planned.
Therefore, since the establishment of ATLA in October
2015, the Department of Project Management in ATLA
undertakes project management throughout the life cycle of
equipment upon selecting important equipment, and promotes
efforts to realize the optimized equipment acquisition.
Specifically, the MOD has selected 18 items for major
programs designated for project management and 6 items
for semi-major programs for project management1 as of the