UAE Information Assurance Regulation
T3.3
System Planning and Acceptance
Objective
To ensure security requirements are properly considered during the
development lifecycle of information systems
Performance Indicator
Percentage of information systems that successfully integrated all system
development lifecycle security requirements
Automation Guidance
Not applicable
Relevant Threats and
Vulnerabilities
•
•
•
T3.3.1
Equipment failure
Illegal processing of data
Use of counterfeit or copied software
Capacity Management
Priority
Applicability
Control
The entity shall manage the required capacity.
Sub-Control
The entity shall:
P4
Based on risk assessment
1) have the ability to measure capacity of current systems and estimate
capacity requirements of planned systems
2) integrate capacity management controls into relevant demand
management and software / system development lifecycle processes
3) make necessary adjustments to capacity to maintain required system
performance
Implementation Guidance (for information purpose only)
For each new and ongoing activity, capacity requirements should be identified. System tuning and
monitoring should be applied to ensure and, where necessary, improve the availability and efficiency of
systems. Detective controls should be put in place to indicate problems in due time. Projections of future
capacity requirements should take account of new business and system requirements and current and
projected trends in the entity’s information processing capabilities.
Particular attention needs to be paid to any resources with long procurement lead times or high costs;
therefore managers should monitor the utilization of key system resources. They should identify trends in
usage, particularly in relation to business applications or management information system tools.
Managers should use this information to identify and avoid potential bottlenecks and dependence on key
personnel that might present a threat to system security or services, and plan appropriate action.
119