Steady Implementation of Measures Concerning the USFJ
8
9
given the utmost consideration for the natural environment.
Throughout the procedures, the MOD received more than
1,500 opinions from the Governor of Okinawa on six
occasions, all of which the MOD reflected in the content of
the environmental assessment.
If the waters are enclosed by the seawall, the coral
will be isolated from the surrounding sea with the flow of
seawater shut down, a situation which will affect the coral
habitat. Therefore, corals living in the land-fill area on the
southern side which were designated for conservation were
transplanted before the area was enclosed.
The standard for conservation of corals is stricter than the
standard that was applied to the land-fill related to the second
runway of Naha Airport.8
Regarding coenobita, which are nationally designated
protected species, and the shellfish and crustaceans designated
as endangered species, relocation from the seashore and
seafloors in the construction area on the southern side to
other areas is also being appropriately implemented based on
instructions and advice from experts.
Regarding the soil foundation of the land-fill area, as a result
of a study conducted on the stability of seawalls and other
structures in the waters north of Camp Schwab in light of the
results of a boring survey, it has been confirmed that although
the work to improve the soil foundation is necessary, it is
possible to implement the construction of seawalls and
land-fill while ensuring the required stability through
prevailing and adequately proven construction methods.9
Since September 2019, the Technical Review Committee
on Futenma Replacement Facility Construction Project,
consisting of experts in the fields of geotechnical, structural,
coastal, and pavement engineering, has been held to obtain
objective technical recommendations and advice in order to
make the design, construction, and maintenance of seawalls
and land-fill sites more rational for the future implementation
of the project. In December 2019, the Okinawa Defense
Bureau announced that, based on the results of the studies
that had been conducted, it would take nine years and three
months from the commencement to the completion of
construction based on the revised plan, and take about 12
years to complete the “admin procedures” described in the
Okinawa Consolidation Plan and a fund of about 930 billion
yen. Hearing experts’ insights on the environment and
others, after due consideration, in April 2020, the Okinawa
Defense Bureau submitted to Okinawa Prefecture a request
for revision of land-fill permit due to addition of the soil
Specifically, in relation to the construction of the second runway of Naha Airport, around 37,000 clusters of small corals were transplanted. If the same standard as the one applicable to
the construction of the alternative facility was applied, the number of clusters of small corals transplanted would have been around 170,000.
The standard methods are the sand compaction pile method, the sand drain method, and the paper drain method. Among examples of projects in which these methods were used is the
construction work to expand Tokyo International Airport (Haneda Airport).
Defense of Japan
328
Chapter
2
Japan-U.S. Alliance
replacement facilities construction project. In April 2017, it
started the construction of the seawall, the main part of the
public waters reclamation.
d. Lawsuit Related to Damage to the Reefs on the Seafloor, Etc.
In July 2017, Okinawa Prefecture filed suit in the Naha
District Court, requesting that this seawall construction not
be allowed to damage the reefs on the seafloor, etc., without
permission from the Governor of Okinawa based on the
regulations of Okinawa Prefecture. Subsequently, the district
court dismissed Okinawa Prefecture’s claim in March 2018,
and the Naha Branch of the Fukuoka High Court dismissed
Okinawa Prefecture’s appeal in December of the same year.
In the same month, Okinawa Prefecture filed a petition
of final appeal with the Supreme Court, but withdrew the
petition in March 2019.
e. Situation Surrounding the Land-Fill Work
In August 2018, Okinawa Prefecture revoked the landfill permit again on the basis of problems concerning
environmental protection measures and the soil foundation of
the land-fill area. In October of the same year, the Okinawa
Defense Bureau filed a request for review and a petition
for a stay of execution under the Administrative Complaint
Review Act against the revocation of the permit, and the stay
of execution was upheld. Following the ruling, the Okinawa
Defense Bureau resumed the land-fill operation in December
of the same year in the waters south of Camp Schwab.
In April 2019, the Minister of Land, Infrastructure,
Transport and Tourism determined that the revocation of the
land-fill permit by Okinawa Prefecture should be repealed.
Dissatisfied with this decision, the Governor of Okinawa filed
a request for a review with the Central and Local Government
Dispute Management Council in the same month. The Council
dismissed this request in June 2019. In July 2019, protesting
the dismissal of the Council, the Governor of Okinawa filed a
lawsuit with the Naha Branch of the Fukuoka High Court to
revoke the government’s involvement (determination by the
Minister of Land, Infrastructure, Transport and Tourism), and
in August 2019 filed a lawsuit with the Naha District Court
seeking the revocation of the determination by the Minister of
Land, Infrastructure, Transport and Tourism. In October 2019,
the Naha Branch of the Fukuoka High Court dismissed the
Governor of Okinawa’s suit. In the same month, the Governor
of Okinawa filed a petition for acceptance of final appeal with
the Supreme Court, which was dismissed in March 2020.
In implementing the relocation, the MOD has conducted
environmental impact assessment for about five years, and
Section 4