Landfill Area 2
Landfill Area 2-1
April 2022
Chapter
2
Landfill Area 2
Landfill Area 2-1
Japan-US Alliance
Progress of landfill work
the Minister of Land, Infrastructure, Transport and Tourism
for a stay of execution under the Administrative Complaint
Review Act against the revocation of the permit, and the
stay of execution was upheld. Following the ruling, the
Okinawa Defense Bureau started the landfill work in
December of the same year in the waters south of Camp
Schwab. In August 2021, the landfill up to 4.0 m above
sea level was completed, and the landfill work is steadily
progressing. (As of May 2022)
In April 2019, the Minister of Land, Infrastructure,
Transport and Tourism determined that the revocation
of the landfill permit by Okinawa Prefecture should be
repealed. Dissatisfied with this decision, the Governor
of Okinawa filed a request for a review with the Central
and Local Government Dispute Management Council in
the same month. The Council dismissed this request in
June 2019. In July 2019, protesting the dismissal of the
Council, the Governor of Okinawa filed a lawsuit with
the Naha Branch of the Fukuoka High Court to revoke the
government’s involvement (determination by the Minister
of Land, Infrastructure, Transport and Tourism), and
in August 2019 filed a suit with the Naha District Court
seeking the revocation of the determination by the Minister
of Land, Infrastructure, Transport and Tourism.
Of these suits, in October of the same year the Naha
Branch of the Fukuoka High Court dismissed the suit by
the Governor of Okinawa to revoke the government’s
involvement, and the Governor of Okinawa filed a petition
7
8
311
for the Supreme Court to take up the appeal, but in March
2020 the Supreme Court rejected the request by the
Governor of Okinawa. On the other hand, with regards
to the suit to revoke the ruling, the Naha District Court
dismissed the request by Okinawa Prefecture in November
2020, and Okinawa Prefecture appealed to the Naha Branch
of the Fukuoka High Court. Ultimately, however, the Naha
Branch of the Fukuoka High Court also dismissed Okinawa
Prefecture’s appeal in December 2021. In that same month,
Okinawa Prefecture filed a petition of final appeal with the
Supreme Court.
In implementing the relocation, the MOD has
conducted environmental impact assessment procedures
for approximately five years and has given the utmost
consideration for the natural environment. Throughout the
procedures, more than 1,500 opinions have been expressed
by the Governor of Okinawa on six occasions, all of which
the MOD reflected in the environmental assessment.
If the waters are enclosed by the seawall, the coral
will be isolated from the surrounding sea with the flow of
seawater shut down, a situation which will affect the coral
habitat. Therefore, corals living in the landfill area on the
southern side, which were designated for conservation,
were transplanted before the area was enclosed. The
standard for conservation of corals is stricter than the
standard that was applied to the landfill related to the
second runway of Naha Airport.7 Regarding coenobita,
which are a nationally designated protected species, and
the shellfish and crustaceans designated as endangered
species, relocation from the seashore and seafloors in the
construction area on the southern side to other areas is also
being appropriately implemented based on instructions and
advice from experts.
Regarding the soil foundation of the landfill area, as a
result of a study conducted on the stability of seawalls and
other structures in the waters north of Camp Schwab in
light of the results of a boring survey, it has been confirmed
that although the work to improve the soil foundation is
necessary, it is possible to implement the construction of
seawalls and landfill while ensuring the required stability
through prevailing and adequately proven construction
methods.8 Since September 2019, the Technical Review
Committee on Futenma Replacement Facility Construction
Project, consisting of experts in the fields of geotechnical,
Specifically, in relation to the construction of the second runway of Naha Airport, around 37,000 clusters of small corals were transplanted. If the same standard as the one applicable to the
construction of the alternative facility was applied, the number of clusters of small corals transplanted would have been around 170,000.
The standard methods are the sand compaction pile method, the sand drain method, and the paper drain method. Among examples of projects in which these methods were used is the
construction work to expand Tokyo International Airport (Haneda Airport).