7.4 FUNDING AND PROCUREMENT
Funding the Plan will always pose challenges.
However it is generally true that international
agencies will support well designed ICT
programmes and that there is often room to
optimise existing resources assigned to ICT
initiatives across government when they are
reviewed as an all-of-government portfolio. The
Steering Advisory Committee (NICTSAF) and the
National ICT Implementation Secretariat (NICTIS)
therefore play critical roles in obtaining funding
for the Plan. It is difficult to determine the cost of
implementing the Plan without considerable
more analysis and doing a more detailed design
of each programme, project, or initiative.
However using a costing by analogy process
based on similar Plans in other island states, the
potential budget for the Plan to 2015 will be in
the order of US$ 25 million. This figure does not
include investments made by the private sector
in its own operations.
7.4.1
Source of Additional Funding or
Cost Savings
Several other avenues for funding will be
investigated and utilised, including the following:
1. Currently the Regulation of the
Telecommunications Sector is fairly well
funded through the collection of spectrum
fees.
2. The regulations of the ICT Sector can also be
funded by similar fees from regulating ICT
services and using the same NTRC / ECTEL
administrative structure.
3. Through the OECS EGRIP, there will be
economies of scale in the regional
procurement of software licenses, the
creation of a regional expert and
applications maintenance team.
4. Leveraging the support of the regional
organisations for attendance at workshops,
ICT industry meetings and advice at:
CARICOM, CTU, ITU, CKLN and CARICAD.
5. Utilize the Taiwan ICT Centre to accelerate
the creation of costly applications and avoid
the cost of some expensive consultants and
technical expertise.
6. Embrace Cloud Computing and Data Services
to reduce costs.
7. Fully establish the Government Backbone to
reduce cost of Government owned Intranet
initiatives
8. Leverage the National ICT Strategy and
Action Plan to obtain funding from donor
organisations
International best practice has also shown that
unless the procurement process within
government is streamlined, the various initiatives
will not align and integrate, and the aggressive
timeline of the implementation will not be
achieved, and ultimately the success of the
integration across government will be stymied. It
is therefore necessary for the National ICT
Implementation Secretariat to work with the
procurement agencies to streamline the processes
within the accepted procurement policies and
laws to ensure that the goods and services
needed for success are procured when required.
7.5
RISK MANAGEMENT
Risk management is about the identification of
the things that can go wrong in the
implementation of the Plan and about designing
plans to manage and mitigate such risks. An
ambitious Plan such as this will be faced with
many risks. These risks vary from lack of
funding, insufficient human resources for
execution, to weak stakeholder support. Some of
the risks as associated mitigated actions are now
considered.
St. Vincent & the Grenadines National ICT Strategy and Action Plan P a g e | 90
One of the major risks is that of insufficient
funding allocated to the implementation effort.
This risk has been addressed in the process of
development of the Plan to some degree, in that
the SWGs were quite inclusive and therefore
would have generated a degree of awareness and
support for the Plan itself, which will facilitate
the funding effort. The probability of this risk
happening is high, using a high/medium/low
scale. However, its impact is considered medium,
using a high/medium/low scale, as some of these
initiatives are already underway and in some
cases available resources can be re-focussed if
needed. The key mitigation strategies for this
risk is to prioritise and focus on the key
initiatives that best support the national
development effort and to do these projects in
the immediate term.
Additionally, the various funding and
development agencies need to be engaged
immediately as they will often support well
designed and managed initiatives. And finally, a
robust mechanism for submitting budget
requests to Government must be developed and
implemented, which will include monitoring
processes, and detailed reporting on
achievements and on the associated outputs,
impacts and outcomes.
The second challenge that the Plan will face is
the potential loss of momentum between the
completion and approval of this Plan and its
implementation. The probability of the risk is
medium but its impact would be high. The
probability of the risk is medium because the
plan itself is supported by key stakeholders,
including senior public officials. The key
mitigating strategy is to move forward with the
quick win initiatives immediately so that
progress is demonstrated even while the Plan is
being formally approved.