(6) The network operator shall make the requested minimum information
referred to in subsection (1) available via the single information point.
(7) In the event of a dispute arising in connection with the rights and
obligations provided for in this Section, either party is entitled to refer it to
the Commissioner who, taking full account of the principle of
proportionality, shall issue a binding decision to resolve the dispute within
the shortest possible timeframe and in any case within two (2) months,
except in exceptional circumstances, without prejudice to the possibility of
any party to refer the case to the Court.
(8)(a) The Commissioner may issue an Order providing for exemptions from
the obligations provided for in this Section for technical works of
insignificant value or in the case of critical national infrastructure.
(b) Such exemptions shall be duly reasoned and interested parties shall be
given the opportunity to comment on the draft exemptions within a
reasonable period.
(c) Any such exemptions shall be notified to the Commission.
(9) Where the Commissioner establishes a violation of the provisions of this
Section, he shall inform the licencee accordingly and may impose an
administrative fine and/or other penalties in accordance with the Order on
the Collection of Information and the Imposition of Administrative Fines.
7 of 104(I) of 2016.
Procedure for the
granting of permit
and/or rights.
96E. (1) All relevant information concerning the conditions and procedures
applicable for granting permits for technical works needed with a view to
deploying elements of high-speed electronic communications networks,
including any information concerning exemptions applicable to such
elements as regards some or all permits required under national law, shall be
196