No. of 2021
67
Telecommunications Bill, 2021
(e) state that all reasonable attempts to seek permission for entry have failed; and in the
case of land owned or controlled by another carrier, state that all reasonable
alternatives for entry on land have been exhausted.
(3) The court may grant an order under this section if it is satisfied that the applicant has
complied with the requirements of sections 79, 80 or 81 as the case may be.
83. Access to lands for inspection and maintenance
(1) In engaging in the inspection of and installation of network facilities, or maintenance of
network facilities, an operator shall take all reasonable steps to act in accordance with good
engineering practice, to protect the environment, to protect the safety of persons and property, and
to ensure that the activity interferes as little as is practicable with the operations of a public utility,
roads and paths, the movement of traffic, and the use of public grounds and other land.
(2) Where, in an exercise of the power conferred by this section, damage is caused to land or
to chattels, the operator shall make good the damage or pay to every person interested in the land
or chattels compensation in respect of the damage.
(3) Where, in consequence of an exercise of that power, a person‘s enjoyment of land or
chattels is disturbed, the operator shall pay to that person compensation in respect of the
disturbance.
84. Damage to installation, repair and restoration
(1) Where an operator in the course of carrying out road works, damages an installation of a
utility, it shall immediately notify the utility owner and make plans to repair the damage to the
utility installation.
(2) The operator shall compensate the utility installation owner for the full cost of repair at
the utility owner’s standard rates, which must be cost oriented.
(3) An operator shall, as speedily as possible, complete all works on, around and by the roads
and public grounds and restore the road and public grounds, including removing any debris, to the
satisfaction of the Minister with responsibility for work and transportation.
(4) Where an operator fails to comply with subsection (3), it shall be held liable for any
expenditure that the Minister referred to in subsection (3) incurs in such restoration and for any
other loss by any other person.
(5) The liability of the operator under sub-section (4) shall continue for a period of 6 months
or until the Ministry expresses its satisfaction in writing pursuant to sub-section (3).